Year |
Date |
Event
|
1967 |
N/A |
Conceptualise of a Rapid Transit Line to ease road congestion issue.[1]
|
1972-1982 |
N/A |
Bus vs Rail Debates.
|
1982 |
28 March |
Government decided to build the MRT.
|
1983 |
14 October |
Established the then MRT Corporation (Now Land Transport Authority).
|
22 October |
Ground-breaking ceremony at Shan Road.
|
1987 |
6 August |
SMRT Corporation was established.
|
7 November |
North–South Line began operation.
|
Yio Chu Kang to Toa Payoh were opened.
|
12 December |
Novena to Outram Park were opened.
|
1988 |
12 March |
Tiong Bahru to Clementi were opened.
|
5 November |
Jurong East to Lakeside were opened.
|
20 December |
Khatib to Yishun were opened.
|
1989 |
4 November |
East–West Line began operation.
|
Separation of North–South Line and East–West Line.
|
Marina Bay was opened.
|
Bugis to Tanah Merah were opened.
|
16 December |
Simei to Pasir Ris were opened.
|
1990 |
10 March |
East–West Line (Branch Extension) began operation.
|
Bukit Batok to Choa Chu Kang were opened.
|
6 July |
Boon Lay was opened.
|
1991 |
February |
Plans for Woodlands Extension.
|
1993 |
N/A |
Construction began for Woodlands Extension.
|
1996 |
10 February |
East–West Line (Branch Extension) dissolved into North–South Line.
|
Yew Tee to Sembawang were opened.
|
2001 |
10 January |
Expo was opened.
|
18 October |
Dover was opened.
|
2002 |
8 February |
Changi Airport was opened.
|
2003 |
20 June |
North East Line began operation.
|
Template:STN to Punggol were opened.
|
2004 |
20 April |
Nicoll Highway collapsed during the construction of Template:STN.
|
December |
Construction began for Boon Lay Extension.
|
2006 |
15 January |
Template:STN was opened.
|
2009 |
28 February |
East–West Line (Boon Lay Extension) began operation.
|
Pioneer to Joo Koon were opened.
|
28 May |
Circle Line began operation.
|
Bartley to Template:STN were opened.
|
December |
Construction began for North South Line Extension.
|
2010 |
17 April |
Dhoby Ghaut to Template:STN were opened.
|
2011 |
20 June |
Template:STN was opened.
|
8 October |
Caldecott to Template:STN were opened.
|
15 December |
5-hours long disruption along North–South Line.
|
17 December |
7-hours long disruption along North–South Line.
|
2012 |
14 January |
Bayfront to Marina Bay were opened.
|
2013 |
22 December |
Downtown Line began operation.
|
Bugis to Chinatown were opened.
|
2014 |
23 November |
North–South Line (North South Line Extension) began operation.
|
Marina South Pier was opened.
|
2015 |
7 July - 8 July |
18-hours long disruption and delay along North–South Line and East–West Line.
|
27 December |
Bukit Panjang to Rochor were opened.
|
2017 |
18 June |
East–West Line (Tuas West Extension) began operation.
|
Gul Circle to Tuas Link were opened.
|
21 October |
Fort Canning to Expo were opened.
|